The new $970 million Robley Rex VA Medical Center on Brownsboro Road won't open until 2028, and the VA now plans to retain the current Zorn Avenue hospital for future use. The project, originally slated for completion in 2026, is now expected to finish construction in April 2027.
LOUISVILLE, Ky. â The Department of Veterans Affairs has confirmed that Louisville's new nearly $1 billion VA hospital will not open until 2028, and officials now say they plan to keep the current hospital on Zorn Avenue.
The new Robley Rex VA Medical Center is under construction at 4906 Brownsboro Road, near Interstate 264. The $970 million project broke ground in 2021 and was originally expected to be completed in 2026.
Construction is now expected to wrap up in April 2027, with the U.S. Army Corps of Engineers expected to formally hand the facility over to the VA no later than June 2027. But veterans won't begin using the VA hospital until 2028.
"The Department of Veterans Affairs plans to retain the facility at 800 Zorn Avenue in Louisville for future use and will announce details as they become available. The Robley Rex VA Medical Center anticipates fully moving operations to the Brownsboro Road location in 2028," the VA said in an emailed statement.
It is unclear how the VA plans to utilize the Zorn Avenue space. The current hospital opened in 1952 and has 117 licensed beds.
The new, 910,115-square-foot hospital will have 104 beds and serve nearly 45,000 veterans across Kentucky and Indiana. Officials previously said it would employ 2,000 people.
The campus will include parking structures, roadway and sidewalk improvements, along with a central utility plant.
As of 2025, the project was about 80% complete.