Kentucky Power has asked state regulators to approve a $2.81 billion natural gas-fired power plant to serve a hyperscale data center planned by TeraWulf in Boyd County, raising concerns about residential utility bills in one of the state's poorest regions.
An investor-owned electric utility serving Eastern Kentucky is asking the Kentucky Public Service Commission for permission to build a $2.81 billion natural gas-fired power plant to supply electricity to a proposed hyperscale data center.
The combined cycle natural gas turbine, capable of generating up to 769 megawatts, would be the first major power plant Kentucky Power has built in decades. The utility serves roughly 162,000 customers across 20 Eastern Kentucky counties and is a subsidiary of Ohio-based American Electric Power.
In a statement, Kentucky Power president and chief operating officer Cindy Wiseman said the utility's commitment to the region "goes beyond providing reliable electricity."
"We've served these communities for generations, and we want our customers and communities to share directly in the benefits when new investment comes to the region," Wiseman said. "Eastern Kentucky has a tremendous opportunity ahead, and thoughtful growth can strengthen our electric system, support good jobs and attract new investment."
The plant would serve a hyperscale data center planned by TeraWulf, an investor-owned company whose facility would demand 1 gigawattâor 1,000 megawattsâof electricity. In its application, Kentucky Power said it compared alternatives including a smaller gas-fired turbine and renewable energy but concluded it needed "a more energy dense resource" to meet the data center's near-constant demand. The utility is seeking to purchase fossil fuel-fired power from elsewhere until the new plant enters service in 2031.
Kentucky Power is also asking regulators to approve a contract with TeraWulf under which the company would pay approximately $100 million over 10 years to offset residential utility bills in the winterâan estimated $26 per month for each ratepayer during that season.
In written testimony, American Electric Power vice president Alex Vaughn said current ratepayers would see no rate increase from the plant's construction. He attributed that to fuel cost savings from the more efficient facility and to the utility collecting more revenue from the TeraWulf data center.
The TeraWulf proposal was unveiled this summer by elected officials in Boyd and Greenup counties for the EastPark industrial parkâthe same site where the state had to claw back a $15 million investment after a failed Braidy Industries aluminum mill. TeraWulf has held public meetings in the months since, hearing concerns from residents about utility bills and environmental impacts. The company has also said it may potentially double the size of the data center and is building another hyperscale facility at a former aluminum smelter in Hancock County.
Suzanne Griffith, a Kentucky Power ratepayer in Boyd County, urged state lawmakers to enact ratepayer protections against data center impacts during an October listening session at the state Capitol Annex. Incoming House Majority Whip Josh Bray, R-Mount Vernon, is looking to pass such a law next year after a bill died this year.
Griffith told the Kentucky Lantern that despite the utility's assurances, she remains worried about the long-term effects of the plant and data center on residential bills.
"People are at their utter limits here in Eastern Kentucky. People send me their bills. They're ridiculously high," Griffith said. "What are they expecting out of us?"
A Kentucky Power spokesperson said the utility's internal rules already protect ratepayers, including a requirement that industrial customers pay for 90% of their contracted electricity capacity every month.
Kentucky Power's residential ratepayers pay among the state's highest average monthly utility bills, and the utility serves some of Kentucky's poorest counties. Poor energy efficiency in the region's housing stock is a factor in electricity bills surging to hundreds of dollars a month for some ratepayers during winter.
The Public Service Commission is also scrutinizing Kentucky Power's planning practices in an ongoing audit. The commission recently gave the utility permission to build a new cooling tower at its coal-fired power plant with the help of a federal grant.