North Carolina regulators approved a two-year Duke Energy rate increase averaging 4.7% annually for residential customers, far below the utility's original request, while also ordering new data center fees and customer refunds. The decision came as the commission separately approved a carbon plan that delays coal retirements and adds natural gas generation, disappointing environmental groups.

Duke Energy Rate Hike Approved by NC Utilities Commission, Adding $6-$10 to Monthly Bills

The North Carolina Utilities Commission on Tuesday approved Duke Energy's request to raise electricity rates, ending months of contentious hearings across the state and setting the stage for higher monthly bills for millions of residents.

The commission ruled that Duke Energy can implement an average annual increase of about 4.7% for residential customers over the next two years. That figure aligns with a settlement Duke reached with the state earlier this year, in which the utility dropped its original request for an 18% increase over two years down to roughly 9.5%.

For a typical residential customer using 1,000 kilowatt-hours per month, the approved increases translate to a $6.53 monthly increase in 2027 and an additional $4.66 in 2028 for Duke Energy Carolinas customers. Duke Energy Progress customers, who make up most of eastern North Carolina, will see increases of $9.62 per month in 2027 and $5.89 in 2028. The two entities are scheduled to merge next year but will maintain separate rates until Duke files future rate requests.

Duke Energy has argued that the increases are necessary to fund infrastructure needed to keep pace with the state's growing population and rising demand from businesses, including manufacturers and data centers. The rate request hearings Duke was required to hold across North Carolina were typically packed with customers objecting to the size of the proposed increase.

Tuesday's decision also included several other provisions. Duke must establish a new rate schedule for data center customers with loads exceeding 50 megawatts, along with upfront payments for infrastructure upgrades. The commission also ordered Duke to refund money with interest to customers if the utility fails to complete planned infrastructure upgrades on time, and set aside $20 million in new funding to assist customers in need.

The rate case unfolded alongside broader debates over how large energy users like data centers should pay for the costly infrastructure required to power them, a discussion that has intensified as North Carolina's energy demands surge.

Separately this week, the utilities commission approved Duke Energy's latest carbon plan, a document the N.C. General Assembly requires the utility to file showing how it intends to reach carbon neutrality by 2050. It is the first carbon plan approved since lawmakers eliminated an initial goal of reducing emissions by 70% by 2030.

In that plan, regulators granted Duke's request to delay some coal plant retirements until 2040 and approved an additional 3,841 megawatts of new natural gas generation between 2030 and 2033. The plan also authorizes Duke to pursue 2,300 megawatts of new solar generation between 2032 and 2034 and to develop up to 2,700 megawatts of additional battery storage. It approves $440 million in advanced nuclear development costs through 2028 and preserves options to build new nuclear plants in the coming years.

Environmental groups, including the Southern Environmental Law Center and the N.C. Sustainable Energy Association, have expressed disappointment with large portions of the carbon plan, objecting to continued investments in coal and natural gas and what they describe as insufficient emphasis on renewable energy sources.