Politics
Mayes Urges Cochise County to Halt SpaceX Data Center Vote, Citing Power, Water and Safety Gaps
Arizona Attorney General Kris Mayes is asking Cochise County's planning commission to postpone its Dec. 9 vote on a $50 billion SpaceX data center campus, warning that state and federal reviews are incomplete and that the project's massive power and water demands remain unexplained.
Arizona Attorney General Kris Mayes is calling on Cochise County to postpone a scheduled Dec. 9 vote on a proposed $50 billion SpaceX data center campus, arguing that state and federal regulators have not yet finished examining the project's consequences for power, water, wildlife and public safety.
In a letter sent Thursday to the Cochise County Planning and Zoning Commission, Mayes said the county should hold off on deciding the project's Special Use Permit until those reviews are complete. "The people of Cochise County deserve answers before county officials approve a project of this magnitude," she said in a written statement.
The request comes as SpaceX, Elon Musk's rocket and artificial intelligence company, pursues what would be Arizona's largest data center campus, a 747-acre facility planned next to the Willcox Playa in southern Arizona. The company announced the project earlier this month, and several community groups have since organized to oppose it.
Mayes's letter lays out a series of concerns, beginning with electricity. The campus would require 1.5 gigawatts at start-up and 6.0 gigawatts at full buildout, according to the letter. The start-up demand alone is 62% larger than the entire owned and contracted generation fleet of the Arizona Electric Power Cooperative, and the cooperative's Apache plant produces roughly 625 megawatts, about one-tenth of the full buildout. While SpaceX has proposed $3.6 billion in grid investments, the letter says the company has not explained how it would close a 4.5-gigawatt gap.
On water, the application states that the campus would be dry-cooled and use only 7 to 10 acre-feet of water annually. Mayes's letter contends that figure excludes the water needed to generate the campus's power, noting that a single 1-gigawatt natural gas plant running continuously withdraws between 3.6 million and 6.8 million gallons per day. The site lies within the Willcox Active Management Area, which the state designated two years ago to curb groundwater depletion.
The letter also flags fire and safety risks. About 6,150 Tesla Megapack batteries would be stored on site, and the campus sits outside any fire district, meaning local responders may need additional equipment and training to handle a battery fire.
Traffic is another concern. Up to 5,500 workers at peak construction, along with heavy truck traffic, would likely accelerate wear on rural two-lane stretches of US-191 and surrounding county roads. Mayes asks the county to commission an independent traffic study and plan for road upgrades before construction begins.
Wildlife and military operations also factor in. The site is immediately adjacent to the Willcox Playa, where thousands of Sandhill Cranes winter and draw tourists. The letter further suggests the U.S. military may need to assess whether the campus's electromagnetic footprint could interfere with Fort Huachuca and Army electronic testing on the playa.
If the county proceeds with the Dec. 9 vote, Mayes recommends at least four conditions: delaying the permit's effective date until SpaceX secures all relevant state and federal authorizations; withholding building permits until those approvals are in place; reviewing the full 6-gigawatt project rather than allowing SpaceX to phase in a larger facility through piecemeal applications; and holding additional public meetings in all affected areas, including the city of Willcox.
Mayes is scheduled to hold a town hall on the project on Thursday, Dec. 3, from 5:30 p.m. to 7 p.m. at Cochise Elementary School. Those interested in attending can RSVP online.