Saturday, November 21, 2026·Focal News

The Phoenix Focal

Phoenix's independent voice

Local

Cochise County Chair: SpaceX Pledges $3.6B Grid Upgrade, No Groundwater for $50B Data Center

SpaceX has promised to spend $3.6 billion on power grid upgrades and use no groundwater at its proposed 6-gigawatt Cochise County data center, Board of Supervisors Chair Frank Antenori said, as Attorney General Kris Mayes urges the county to delay a key land-use vote.

Cochise County Chair: SpaceX Pledges $3.6B Grid Upgrade, No Groundwater for $50B Data Center

WILLCOX, Ariz. — SpaceX has committed to spending $3.6 billion to upgrade the power grid and to use no groundwater at its proposed $50 billion data center campus in Cochise County, according to the chair of the county Board of Supervisors, as Arizona's attorney general presses the county to slow down its review.

Board of Supervisors Chair Frank Antenori said the company's assurances address several concerns county officials raised about the project, which SpaceX calls its Cochise Supercomputer Campus. The hyperscale facility would span nearly 750 acres and, at full build-out, consume 6 gigawatts of electricity — nearly 20% of Arizona's total power-generating capacity, according to Attorney General Kris Mayes.

Antenori said he was taken aback when he first learned SpaceX was eyeing the county. "I didn't believe it," he said. "It was a big surprise. Hard to believe. And now it's looking pretty good."

According to the company's application, the campus would consist of nine buildings of 500,000 square feet each. Beyond the grid investment and the no-groundwater pledge, Antenori said SpaceX has agreed to follow the county's dark-sky rules, which limit light pollution.

Mayes has asked the county's Planning and Zoning Commission to delay its land-use vote on the project, which is scheduled for about three weeks from now, citing the scale of the power demand. The commission must approve the land use before the county can negotiate a binding development agreement and the developer can seek a building permit. County officials estimate the process could wrap up by April or May.

Arizona's Family Investigates contacted all nine members of the commission. Some said they had not heard of the letter or the request, and none said they would respond immediately. A county public information officer said the county had no new information to report.

Antenori said the project would mean roughly 1,000 jobs at full build-out, about half of which could be filled by people right out of high school, plus another 1,500 secondary jobs. SpaceX originally provided the jobs estimate. Greg Wright, a professor at the University of California, Merced, who co-authored a Brookings Institution paper on data center employment, called the direct-jobs figure plausible but questioned the secondary estimate.

"That sounds a little high to me for a small rural community, but it could be something there," Wright said.

Both Antenori and Wright said the project could bolster county finances. "It will definitely benefit our schools and our hospital districts, our fire districts and whatnot in the county," Antenori said.

The proposal comes as rural counties across the West weigh the promised tax revenue and jobs of large-scale computing facilities against their heavy demands on electricity and water — resources that are increasingly strained in Arizona. The 6-gigawatt load, if built, would make the campus one of the largest single power consumers in the state and would require substantial new transmission capacity, which the company's $3.6 billion pledge is meant to help finance.