Local
Ahwatukee Residents File $11 Million Claim to Halt Menlo Digital Data Center, Alleging Fast-Tracked Permits and Backroom Deals
A group of Ahwatukee homeowners has filed an $11 million notice of claim against Phoenix, seeking to stop construction of a massive Menlo Digital data center they say was approved through rubber-stamped permits and backroom deals. The claim, a precursor to a lawsuit, cites lost property value, noise, pollution, and other nuisances from the 38-acre project.
PHOENIX â Homeowners in Ahwatukee have filed an $11 million notice of claim against the city of Phoenix in an effort to halt construction of a hyperscale data center they allege was fast-tracked through rubber-stamped permits and backroom deals, according to attorneys representing the residents.
The claim, filed Nov. 20, is a required precursor to a lawsuit and gives the group 180 days to file suit. It seeks $1 million split between two households for lost property value and $10 million in nuisance damages for neighbors in the Ahwatukee Community Alliance, citing noise, lights, pollution, traffic, and heat from the project.
The Menlo Digital data center is under construction on a 38-acre site near hundreds of homes. The facility will include a 1 million-square-foot computer warehouseâmore than half the size of State Farm Stadiumâand is designed to generate 257 megawatts, enough to power roughly 58,000 Arizona homes during the summer months.
Tom Branch, who has lived in his home for nearly 30 years, said moving is not a realistic option. "Of course, we thought about it, but itâs a tough market right now for selling and buying, and itâs not really much of an option for us," he said.
Anthony Ramirez, an Ahwatukee resident and attorney involved in the claim, pushed back on characterizations of the group as anti-technology or environmental activists. "There are people that think that this group is an environmental group, and anti-technology, and thatâs not it at all," Ramirez said. "This is about a data center being built right across the street from homes."
Attorney Jacob Leavitt described the daily impact on residents. "These peopleâs lives currently are being disrupted. Have you ever sat in your home while the ground is vibrating from earth movers? This is a problem," he said.
The residents and their attorneys allege the project was expedited through zoning workarounds and undisclosed deals, claims they hope to prove in court before construction is complete.
"Weâd like to get it stopped. It shouldnât be built here in the first place," Branch said. "I donât care if they store hay in that building, but I donât want it to be a data center."
The city of Phoenix declined to comment, citing pending litigation.
The dispute highlights growing tensions over the rapid expansion of energy-intensive data centers across the Valley, as communities grapple with the local impacts of massive digital infrastructure projects.