A Philadelphia judge ruled that a former operations supervisor at the Reworld incinerator in Chester can testify at a City Council hearing Wednesday, where council is set to vote on a new trash disposal contract. The ex-employee alleges plant managers pushed sulfur dioxide emissions toward the legal limit.

Judge Clears Former Reworld Supervisor to Testify at Philadelphia City Council Hearing on Trash Contract

A former operations supervisor at the Reworld trash incinerator in Chester will be allowed to testify at a Philadelphia City Council hearing on Wednesday, after a Court of Common Pleas judge rejected the company's emergency bid to block his subpoena.

The ruling sets up a high-stakes public airing of allegations about plant operations just as Council prepares to vote on a new waste disposal contract that would keep Philadelphia sending much of its trash to the Delaware County facility.

City Council subpoenaed Eric Bazis, who worked as an operations supervisor at the Chester plant, to provide information at the hearing. Lawyers for Reworld argued that a confidentiality order tied to ongoing federal litigation barred Bazis from testifying. Attorneys for Bazis and the city countered that he would not discuss any information obtained through the discovery process in that lawsuit.

The city's attorney characterized the company's position as a "gag order" and said Council is not seeking confidential material. Reworld's lawyers told the judge they would be unable to object to Bazis's testimony because of how City Council proceedings are structured. The judge ultimately ruled in the city's favor, allowing the testimony to proceed.

According to the lawsuit, Bazis reported that plant managers instructed him "to set filtration settings to emit sulfur dioxide, a harmful pollutant, as close to the legal concentration limit at that plant of 29 parts per million (ppm) as possible," a practice that he said sometimes pushed emissions temporarily above the legal limit.

The hearing is scheduled for 1 p.m. Wednesday, when Council plans to vote on the trash contract.

Philadelphia officials have said decisions about managing the city's waste are driven by cost. The Chester facility remains one of the cheapest disposal options available to the city, according to City Council documents. Under the proposed new waste contracts, Reworld would charge $47 per ton in 2027, making it the second-least expensive disposal facility listed in the proposal, behind only a facility in Conestoga in Lancaster County.

Some Chester residents and Philadelphia officials have called on the city to end its reliance on the incinerator, arguing that the surrounding community bears the health and environmental costs of the pollution. Councilmember Jamie Gauthier has argued for eliminating the city's use of trash incinerators, which can pollute the air.

The vote and the testimony come as Philadelphia weighs the economic appeal of a lower-cost disposal option against the environmental and public health concerns raised by residents and advocates in Chester, a city that has long hosted industrial facilities along the Delaware River.