Tennessee Data Centers Get Tax Breaks While Residents and Lawmakers Demand Answers

Gallatin residents say Meta's massive data center has brought noise and little financial benefit, as a new investigation reveals Tennessee cannot quantify the tax revenue it forgoes and residents struggle to learn basic details about proposed projects.

Tennessee Data Centers Get Tax Breaks While Residents and Lawmakers Demand Answers

GALLATIN, Tenn. — Gerry Dickson has lived in his home since 1989, but the quiet he once knew is gone. Less than a mile away, a sprawling Meta data center campus now hums day and night on more than 800 acres of former farmland.

"They took our peace and they took our quiet," Dickson said.

When Gallatin leaders landed the Meta project in 2020, they celebrated it as one of the largest economic development deals in the city's history, offering substantial property tax incentives to secure it. The campus opened in November 2024 and is slated to include up to 12 data halls spanning 1.5 million square feet, requiring about 300 megawatts of electricity — enough to power up to 300,000 homes.

Six years later, Gallatin has imposed a six-month moratorium on new data centers, and officials are divided over whether the city is getting a fair return.

Meta has invested more than $1.5 billion in the campus. But records show the company paid $2.45 million in lieu of property taxes during the 2025-26 fiscal year, up from $1.75 million the year before. Of that, about $1 million went to Sumner County Schools, $637,000 to Sumner County and just $531,000 to Gallatin.

The payments stem from a 2020 incentive package that provided Meta an estimated $19.5 million in local tax breaks. Instead of conventional property taxes, Meta makes negotiated payments in lieu of taxes, known as PILOTs, with each qualifying building receiving a separate 20-year abatement. The agreement contains no formula for dividing the money among the city, county and schools; instead, Gallatin's Industrial Development Board decides each year how much each entity receives.

Councilman Pascal Jouvence argues Gallatin is getting far less than officials anticipated. "I still don't think we're getting a deal at all," he said.

Rosemary Bates, executive director of Gallatin's Economic Development Agency, disagrees. She points to school funding, community programs and Meta donations of computers, internet hot spots and educational grants. The campus employs about 100 people, according to Meta.

"We are exponentially better financially because of them," Bates said.

Mayor Paige Brown remains supportive of data center development and praised Meta as a good corporate partner, but acknowledged the city's approach has evolved. "Certainly if (the deal) were done today, it would be negotiated very differently," she said.

Beyond finances, the campus has raised questions about water and electricity. Records show Meta used 53.4 million gallons of water in 2025, averaging about 4.5 million gallons a month, drawn from Old Hickory Lake through the city's municipal system. The campus accounted for roughly 2% of Gallatin's water sales and consistently ranks among the city's largest water customers. City officials say supply is sufficient and Meta paid for water and sewer improvements.

Electricity is another matter. Meta receives power directly from the Tennessee Valley Authority, but Bates said Gallatin lacks the infrastructure to support another large power user on a separate 600-acre tract being annexed for future industrial development. A new substation could take at least three years to build. "We can't really have another large electric user for several more years," she said.

For-sale signs have appeared in neighborhoods near the campus. Jim and Maria Joseph, whose backyard borders Meta's property, said construction brought noise and muddy runoff that left portions of their land persistently wet. "Our back lot, since then, it's always muddy," Maria Joseph said, adding that Meta took steps to address complaints. The couple remember when deer and wild turkeys roamed the farmland. Now Maria worries about property values. "It's just hard not knowing," she said.

Gallatin is not alone. Tennessee has about 65 data centers of varying sizes, including major campuses operated by xAI in Memphis and Google in Clarksville, with more proposed amid the artificial intelligence boom.

At the state level, Tennessee offers substantial tax breaks but cannot say how much they cost taxpayers or publicly identify the companies receiving them. The Department of Revenue says 15 companies hold 25 active data center tax exemption certificates, yet the agency does not track total forgone revenue. Data centers investing more than $100 million and creating at least 15 full-time jobs can avoid state and local sales taxes on computer equipment, repairs and backup power infrastructure, and pay a reduced 1.5% state sales tax rate on electricity.

The department declined to identify the companies or provide a county-by-county breakdown, citing taxpayer confidentiality. It said it audits for compliance and has found purchases that did not qualify, but did not say whether any certificates have been revoked or assess what the state is getting in return.

State Rep. Aftyn Behn, D-Nashville, has proposed legislation for 2027 that would freeze new data center tax exemptions for three years and require public reporting on their cost, recipients and compliance. "We're handing multi-million-dollar corporations an exemption our Department of Revenue can't quantify due to inaction from the Legislature, while working people in this state are struggling to pay for groceries," Behn said in a statement.

Tech industries are also expanding their political influence. A review of lobbying records found Anthropic registered six Tennessee lobbyists in 2026 after having none the previous year. OpenAI added three, the Data Center Coalition added one and DC BLOX registered three. Employees and executives affiliated with AI companies contributed at least $131,000 to Gov.-elect Marsha Blackburn's campaign, while Anthropic gave $250,000 to a political action committee supporting her, according to campaign finance records.

In Nashville, battles over two proposed data centers have raised questions about electricity use and transparency. Records show Nashville Electric Service evaluated a DC BLOX project next to the Nashville Zoo at up to 100 megawatts — double the roughly 50 megawatts described to the public and in city planning documents. The utility said the higher figure was an early planning scenario; DC BLOX said plans changed and projected use would be significantly lower but declined to provide an updated figure. The controversy helped prompt new zoning restrictions and a temporary moratorium through Dec. 1. DC BLOX sued the city in August; a federal judge dismissed the lawsuit Oct. 6 but allowed the company to amend its complaint.

Fisk University's planned 30-megawatt facility, part of its $1 billion Quantum Leap development, has drawn skepticism from North Nashville residents who question who might occupy it, how much electricity it would consume and what environmental impacts could follow. University officials say they have not yet secured an operator or occupant.

In rural Lawrenceburg, about 80 miles southwest of Nashville, ScalePoint Infrastructure plans a 4.99-megawatt facility on about 6.5 acres along Flatwoods Road — just below the Tennessee Valley Authority's 5-megawatt threshold for reviewing certain large power requests. Local utility officials say existing infrastructure can support the project and a closed-loop cooling system would limit water use, but residents still don't know who will occupy the facility or whether it could expand.

In July, resident Elle McCann presented the Planning Commission with a petition signed by more than 7,600 people demanding an 18-month moratorium. "We are not anti-business," she told commissioners. "We just want to make sure the right process has been followed and that we're not going to harm Lawrence County for future generations." The commission unanimously approved the site plans, and moratorium efforts went nowhere. Records requests for nondisclosure agreements or discussions involving city officials and the developer turned up no responsive documents.

Lawrence County Chamber of Commerce CEO Ryan Egly defended the project, saying the county offered no tax incentives and expects it to generate revenue without major demands on local infrastructure. The developer has yet to break ground, leaving residents watching and waiting for answers.