The JEA Board approved a plan to fix the utility's failure to collect additional capacity fees from large commercial customers, but a four-year statute of limitations means most of the estimated $55 million in lost revenue may never be recovered.
JACKSONVILLE, Fla. â The JEA Board this week approved a plan to address the utility's failure to collect additional capacity fees from large commercial customers, a problem that went undetected for decades and may have cost tens of millions of dollars.
The issue came to light in March, when it was discovered that JEA had not been charging the fees, which are triggered when a commercial customer's usage exceeds a 20% threshold and involves a change in use or expansion of operations. City Council auditors estimated that as much as $55 million may have been left uncollected over the years.
However, JEA has indicated it will likely be unable to recoup most of that money. A four-year statute of limitations on fee collection prevents the utility from billing for older charges. JEA will begin a reconciliation process in January to determine what it can collect going back to 2023, with that process expected to be completed next September.
JEA also disputed the auditors' $55 million figure, arguing it was likely inflated because auditors only considered one of the two conditions required to trigger the fee.
"Those calculations considered the 20% usage threshold but did not consistently account for the second required condition under the existing tariff, a change in use or an expansion of operations," a JEA spokesperson said in an emailed statement. "Because both conditions must be satisfied for the additional capacity fee to apply, estimates that considered only the 20% threshold potentially overestimated the potential fees owed and may have been artificially high."
Still, JEA does not know the true total and does not plan to calculate the full scope of the historical failure.
"We have to deal with the numbers that we have and clearly make sure through our auditors that this process is solid going forward so we don't get into this position again and collect whatever we can on the past capacity fees," said Jacksonville City Councilmember Ron Salem, who was the JEA liaison when the issue was uncovered and helped lead the council's investigation.
Salem expressed frustration with the oversight.
"What's very important to me is that we have a process going forward that we make sure we're collecting these things. It's a shame that it happened," he said.
A new collection policy will take effect in 2027, under which JEA will notify customers if their usage increases to a level that could trigger additional fees.
Mayor Donna Deegan's office said it supports the fix.
"The JEA Board and staff have done productive work on this issue. Clear, consistent policies help make sure growth is managed fairly and responsibly. We also thank the City Council and the Inspector General for their attention to this matter," a spokesperson for the mayor's office said.
Salem said the plan is the best available solution to a problem that should have been addressed years ago, and he voiced optimism about the utility's future leadership.
"I'm optimistic that the board is gonna open up a wide net and get a CEO in here as quickly as we can, but with the qualifications on water and electricity to move JEA forward," he said.
The reconciliation process is expected to be completed next September.