Mayor Brandon Scott released a 25-year agreement with MCB Real Estate to redevelop Harborplace, offering a $10 million community fund and union guarantees in exchange for a 95% property tax break worth $366 million. Critics question the profit-sharing terms and the fast-tracked Board of Estimates vote.
Mayor Brandon Scott on Thursday released the terms of a 25-year agreement with developer MCB Real Estate to redevelop Harborplace, a package that pairs a sweeping property tax break with a set of community commitments intended to answer critics of the high-profile waterfront project.
The centerpiece of the developer's benefit is a 95% reduction in property taxes over the life of the deal, a subsidy valued at $366 million. In exchange, the city secured a 10-year, $10 million fund for neighborhood initiatives such as summer youth programs, graffiti removal and public events near the harbor; a collective bargaining agreement with AFSCME ensuring union labor at the site; a pledge that 10% of planned apartments will be affordable; and a guarantee that the city will collect at least $543,000 a year in property taxes.
City officials also projected the complex would generate billions of dollars in economic activity.
Scott framed the agreement as a departure from past practices. "My main priority from day one of these negotiations has been getting a good deal for our residents," he said in a statement. "Over my lifetime, I've seen countless deals that advantaged private developers at Baltimore's expense, and I was committed to doing things differently in this negotiation."
In a social media video, Scott and Baltimore Development Corporation President and CEO Otis Rolley III contrasted the terms with the 1980s deal that created the original Harborplace pavilions and promenade. "The old deal had zero community commitments," Rolley said, adding that the new agreement includes "strong accountability and public reporting requirements."
The announcement lands as Rolley, the mayor's point person on the project, faces scrutiny over his personal finances. As reported this week, Rolley owes more than $418,000 in state and federal income taxes. Scott has said he retains confidence in Rolley, whom he appointed in June 2025, and praised his work winning legislative approval of a tax incentive program for downtown projects that MCB principal P. David Bramble has said is essential to the Harborplace plan.
The agreement states that MCB cannot begin construction without demonstrating to the city's satisfaction that it has secured financing to complete each phase. That provision appears aimed at addressing fears that the developer could demolish the two low-rise pavilions and then run out of moneyâa concern at the heart of a lawsuit by residents seeking a preliminary injunction to block demolition.
Online critics quickly zeroed in on the language. "If they have secured the funding to put a big hole in the ground, which would be the first phase of the project, then they can go ahead and do that," one commenter wrote. "Even though they don't have the funding to actually build anything."
Another observer questioned the profit-sharing provision, noting it applies only if MCB exceeds a 20% profit threshold the developer has predicted it will never reach. The same critic pointed out that the community benefits advisory board will be appointed by the mayor, with seven seats, and MCB, with three.
Others objected to the pace of the process. The agreement is scheduled for a vote at the Board of Estimates meeting on Wednesday, December 2, 2026, at 9 a.m. Meetings are open to the public and livestreamed on CharmTV.
"No hearings, no discussions, no transparency," a moderator of the Harborplace Forum Facebook page wrote. "Just the BOE vote on December 2 and we all know how that goes."
The deal echoes earlier publicly subsidized projects that drew similar promises. The city's $660 million tax increment financing package for Port Covington, approved by the City Council in 2016 when Scott was a councilman, was projected to transform a swath of the peninsula. Last December, Under Armour founder Kevin Plank walked away from the project after completing just 1.2 million square feet of the originally projected 18 million square feet of residential and commercial construction.