MDTA Board Approves $38.6M Contract to Clear Remaining Key Bridge Wreckage
The Maryland Transportation Authority awarded a $38.6 million contract to Joseph B. Fay Company for demolition and marine work on the Francis Scott Key Bridge rebuild, with crews set to begin removing remaining span sections over the Patapsco River later this fall.
BALTIMORE â The Maryland Transportation Authority Board on Thursday approved a $38.6 million contract for demolition and marine work tied to the rebuilding of the Francis Scott Key Bridge, the latest step in the effort to replace the span that collapsed into the Patapsco River.
The contract went to Joseph B. Fay Company, and the work is expected to begin later this fall, according to the Maryland Department of Transportation. Bids were received at the end of October, and the authority said it awarded the contract to the lowest-priced, qualified bidder.
The scope of the contract covers removal of the remaining sections of the former bridge over the Patapsco River, demolition of marine and land piers, underwater demolition, and steel pipe pile clean-out needed to make way for the new structure.
Maryland Transportation Secretary and MDTA Board Chair Katie Thomson said the pace of the award reflects the administration's commitment to the rebuild.
"The Moore-Miller Administration has promised to work expeditiously to rebuild the Key Bridge, and the speed with which the MDTA moved to award this contract is a testament to our commitment," Thomson said.
Thomson also said construction is already underway. "Work is actively taking place on the Key Bridge Rebuild, as residents and businesses have observed," she said. "The demolition and marine work associated with the newly awarded contract is expected to begin later this fall and MDTA is advancing three other procurements while construction is underway."
MDTA Executive Director Bruce Gartner described the award as another milestone. "This contract award represents another step forward in our commitment to rebuilding the Key Bridge as quickly, safely and cost-effectively as possible," he said.
Crews have already finished removing the land-based portions of the former bridge, including more than 20,000 tons of concrete decking and columns and steel girders on the north and south sides.
The authority also launched an online interactive tool at KeyBridgeRebuild.com that shows the bridge's three sections and includes photos and details of its elements.
In May, MDTA announced it plans to deliver the remaining rebuild work through four contracts. The authority is still working toward its goal of opening the new Key Bridge to traffic by 2030.
The contract award comes as the region continues to grapple with the loss of a critical crossing that carried traffic over the Patapsco River and served as a key link for commuters, freight and port activity. The rebuild's timeline and cost remain central concerns for residents and businesses that have adjusted to detours and altered travel patterns since the bridge went down.