Maryland taps Joseph B. Fay Co. for $38.6M Key Bridge debris removal
The Maryland Transportation Authority Board approved a $38.6 million contract Thursday with Joseph B. Fay Company to clear remaining steel, piers and underwater foundations from the Patapsco River, with work set to begin in December. The bid came in far below the agency's $92 million estimate as the state pushes toward a 2030 opening for the replacement span.
Maryland's transportation board on Thursday awarded a $38.6 million contract to Joseph B. Fay Company, part of S&B USA Construction, to remove the last remnants of the fallen Francis Scott Key Bridge from the Patapsco River, clearing the way for a replacement span that officials still aim to open to traffic in 2030.
The Maryland Transportation Authority Board approved the contract, and crews are expected to begin work in December. The job carries a 671-calendar-day duration from the notice to proceed.
The scope is substantial: removing and salvaging remaining steel girder sections near both riverbanks, demolishing eight marine piers and two land piers, extracting nine underwater foundations, and cleaning out steel pipe piles that will later be filled with concrete as part of the new bridge's substructure.
The company's roughly $38.6 million bid came in well below MDTA's nearly $92 million estimate, according to board documents â a gap of more than $53 million that could ease pressure on a rebuild whose overall price tag is projected at $4.3 billion to $5.2 billion.
The award follows demolition work completed in February, when crews finished removing the land-based portions of the former bridge, including more than 20,000 tons of concrete decking and columns along with steel girders from both sides of the river.
The original Key Bridge collapsed in March 2024 after the cargo ship Dali struck a support pier, killing six construction workers. The disaster severed a critical Baltimore harbor crossing and triggered a massive salvage and rebuilding effort.
Construction of the replacement is proceeding in parallel. Crews are installing permanent foundation and pier-protection piles, and the temporary trestles that give workers and equipment access over the water were completed in October.
The demolition contract is the first of four separate procurements MDTA is using to complete the rebuild. The others cover the north land approach, the south land approach, and the bridge's main span and marine approaches. Maryland shifted to that multi-contract approach after deciding in April not to retain Kiewit Infrastructure Company for the project's full construction phase when the two sides could not reach an agreement.
The replacement is expected to be Maryland's first highway cable-stayed bridge, with two lanes in each direction, a 1,665-foot main span and at least 230 feet of clearance above the federal navigation channel.
MDTA says the schedule will become clearer as the remaining contracts are awarded. The agency also launched a new interactive feature on KeyBridgeRebuild.com that lets the public explore the north and south approaches, main span, foundations, pylons and pier-protection systems.