King County Council Moves to Withhold $100K Over Capitol Hill Crisis Center Cost Overruns

The King County Council's budget committee voted to withhold $100,000 until the county explains why renovation costs for a planned Capitol Hill mental health crisis center have more than doubled to $35 million. Council members cited a pattern of underestimating project costs and raised concerns about the impact on the county's $1.25 billion crisis care levy.

King County Council Moves to Withhold $100K Over Capitol Hill Crisis Center Cost Overruns

The Metropolitan King County Council's budget committee is demanding detailed answers about a steep increase in renovation costs for a planned mental health crisis center on Capitol Hill, voting Monday to withhold $100,000 in funding until the county provides a full accounting of the project's finances.

The renovation budget for the 60-year-old building at 1145 Broadway has climbed to $35 million, more than double the $17 million estimate the council received when it approved the building's purchase in fall 2025. King County officials attributed the increase to inflation and supply chain pressures, saying the earlier figure reflected costs at the time.

The Budget and Fiscal Management Committee's action requires the county to produce a report analyzing what drove the costs up and a detailed projection of the total renovation expense before the withheld funds are released. The report must also assess how the higher costs could affect implementation of the county's crisis care levy, a $1.25 billion property tax measure voters approved in 2023 to fund a network of five crisis centers.

Additionally, the analysis must cover anticipated costs and revenues for portions of the building not slated for the crisis center. The center is expected to occupy 25,000 to 35,000 square feet of the building's nearly 115,000 rentable square feet. The county plans to build a 16-bed mental health residential treatment facility on another floor and lease out remaining space.

Committee Vice Chair Jorge Barón, who sponsored the budget amendment, said he wanted to avoid delaying the project while still exercising oversight.

"I wanted to be careful, because I don't want to slow things down in terms of getting the work done," Barón said during the meeting. "We want those facilities to move forward, but I think it was also concerning to see the level of escalation."

"I think it's important as part of our oversight duties that we make sure to be getting good information as to these projects," he added.

Committee Chair Rod Dembowski pointed to a broader pattern of county projects coming in over budget, citing the expansion of Harborview Medical Center, where costs have risen more than 70% since voters approved the project in 2020.

"I think that we have some work to do here at the county to … get us into a place where we can have better, more accurate estimates on what it's going to cost to build something," Dembowski said. "I'm still waiting for the project that costs less than we were told it's going to cost at the beginning."

King County paid $41.5 million last year for the former Polyclinic building, which will become a walk-in mental health center. The purchase drew some community pushback over whether a busy section of Capitol Hill already grappling with drug use, disorder and crime was the right location.

The Capitol Hill facility is one of five crisis centers planned countywide, designed to expand access to mental health care regardless of insurance status or ability to pay. Each center will offer multiple levels of mental health and substance-use care, from urgent-care appointments to short stays of up to 14 days. One center, in Kirkland, is already open, and the county aims to have all five operating by 2030.

Following Monday's vote, the budget moves out of committee for discussion and approval by the full council.