Oregon's Clean Energy Fast-Track Option Draws Only Two Projects as State Approval Times Lag
A 2026 law letting clean energy developers bypass state review for county approval has been used by just two projects, both of which won permits in months. Meanwhile, Oregon ranks last in the nation for wind and solar permitting speed, raising doubts about its 2040 carbon-free goal.
A new Oregon law designed to speed up approvals for renewable energy projects has seen limited uptake, with only two developers opting to shift their applications from the state to county jurisdictions, according to state officials.
House Bill 4031, passed by the Legislature in February, allows certain clean energy projects to skip the state's Energy Facility Siting Council and instead seek approval directly from the counties where they would be built. The measure was driven by mounting frustration over state delays and by federal tax credit deadlines set in Congress' One Big Beautiful Bill Act.
The Oregon Department of Energy identified seven projects eligible to make the switch. So far, only two have: the Well Springs Solar Project in Morrow County and a 69-turbine wind farm in Gilliam County. Both received county approval in September, completing a process that took months rather than years.
Brian Walsh, vice president of project development for MN8 Energy, which is behind Well Springs, estimated the move to county jurisdiction cut more than a year off the siting timeline. "That's a tremendous savings for the project," Walsh said, "and also keeps the price of power lower for those who buy the power and consume the power."
The state's track record provided the impetus for the change. A report released earlier this year by the U.S. Department of Energy's Berkeley Lab found that Oregon ranks last among states studied for wind and solar approval times. While 90% of projects in the 19 states with a state approval apparatus secured permits within about a year, Oregon projects took an average of 600 days to reach a decisionânearly double the time of other statesâand could spend nearly as long in a pre-application stage.
"We are 47th in the nation for the production of new clean energy, partly because we make it harder to do than any other state," state Rep. Mark Gamba (D-Milwaukie) wrote to a state agency in September. Gamba said he wants to tighten the state's process in the 2027 legislative session.
State Rep. John Lively (D-Springfield), who chaired the House Interim Committee on Climate, Energy, and Environment that recommended HB 4031, described the state's process as "methodical." He said local officials can act faster because they follow their own codes. "At the local level, you've got local elected officials and staff that are in a position just to act much quicker," Lively said. "Now, you can argue whether they're as thorough as they should be or not. The reality is, they follow the code, so they're doing what the code requires them to do."
Opposition to the two projects that went through county review was minimal: none for the Gilliam County wind farm and only one formal objection to Well Springs.
Ethan Kirkham, a Portland-based senior research analyst at Greenlight America, which helps clean energy proponents organize grassroots support, said counties are more "streamlined" than the state, where projects can go "back and forth for one to three to four to five years."
Thirteen other clean energy projects did not qualify for county approval under HB 4031 and remain in the state's queue. One example: the Yellow Rosebush Energy Center, a solar farm planned primarily in Wasco County, was first pitched to the state in 2023 and won siting council approval on Sept. 18.
Even if only one or two projects are completed in time to capture federal tax credits, Lively said, the law will have been worth it. Still, he acknowledged, "it would be nice to see more."
The slow pace carries high stakes for Oregon's climate commitments. In 2021, the state set a goal of carbon-free electricity by 2040. With permitting timelines among the longest in the country and few projects taking advantage of the new local pathway, that target faces significant headwinds.