Nashville Electric Service Overhauls Storm Response After January Ice Storm Blacked Out 230,000 Homes
Nashville Electric Service says it will issue earlier restoration estimates, pre-arrange outside crews and trim trees farther from power lines after an independent review found its January ice storm response was too slow. The changes come as the utility faces scrutiny over a 12-day outage that left more than 230,000 customers in the dark.
NASHVILLE â Nashville Electric Service is promising faster, clearer communication and earlier outside help the next time a major winter storm hits, following an independent review that faulted the utility's response to January's ice storm, which knocked out power to more than 230,000 customers.
In a message to customers dated Wednesday, Nov. 25, NES President and CEO Teresa Broyles-Aplin outlined a series of operational changes, including early systemwide restoration estimates, expanded call center capacity and more aggressive tree trimming along overhead lines.
Under the new approach, NES will issue a broad estimate for restoring power across its service territory shortly after a major storm, then follow with area-specific estimates as crews assess damage. If an area's estimate changes, customers will receive a text message alert, Broyles-Aplin said.
The reforms respond directly to findings from an independent review of the January storm, which concluded that NES did not request outside crews early or broadly enough. The review estimated that earlier mutual aid could have shortened restoration by two to five days. It took NES 12 days to fully restore service after the storm.
The review also found that the utility failed to provide restoration estimates for roughly the first week of the outage and that several customer information channels broke down under demand.
Broyles-Aplin said NES will now calculate how many crews a storm may require before it arrives and request help in advance. Contracts with outside line, tree and damage-assessment crews are already in place, she said. The utility's outage map and phone system have been upgraded to handle more simultaneous users, and additional call center staff will be brought on for major storms.
The CEO also said crews have worked with certified arborists to trim trees farther back from power lines, part of an effort to manage vegetation along more than 4,500 miles of overhead lines. In September, NES acknowledged it had fallen behind on its new trimming schedule, completing 89 miles through August against a target of 258 miles. The Nov. 25 message did not say whether the utility had caught up.
The changes arrive amid continued scrutiny of NES. Thousands of customers faced possible disconnection this month over unpaid ice storm bills, and a resolution to oust the utility's CEO has returned to the Metro Council agenda.
For residents who endured nearly two weeks without heat and light last winter, the test will be whether the promised improvements hold when the next storm arrives.