16th Street Bridge Full Reopening Pushed to June 2027, Citing Steel Shortages

Milwaukee's 16th Street Bridge will remain partially closed until June 2027 due to unexpected steel replacement needs and procurement delays, frustrating Menomonee Valley businesses and residents already coping with multiple bridge closures.

16th Street Bridge Full Reopening Pushed to June 2027, Citing Steel Shortages

Milwaukee's 16th Street Bridge will remain partially closed until June 2027, city officials confirmed this week, pushing back a full reopening that was originally expected in October and later December. The delay stems from a greater-than-anticipated need for replacement steel discovered during construction, according to the Department of Public Works.

"During the removal and repair phases of construction, the project team identified a greater need for replacement steel than originally anticipated," said Tiffany Shepherd, marketing and communications officer for the department, in an email Tuesday. "The extended procurement lead times for the additional steel materials are the primary factor contributing to the revised project schedule."

The steel shortage is not unique to Milwaukee. Industries nationwide are grappling with decreased steel imports and rising prices, partly due to tariffs. The city and the Wisconsin Department of Transportation are working with the contractor to finalize a revised timeline, Shepherd said, with an official update expected once a new contract completion date is set.

The bridge over the Menomonee River was partially closed last October and fully closed last December after an inspection revealed a compromised structural floor beam. The southern section reopened in August from South 16th and West Pierce streets to Canal Street, restoring access to the Menomonee Valley and downtown via West Clybourn Street.

For businesses in the Menomonee Valley, the extended closure adds to existing disruptions. Paul Bell, vice president of Law Tanning LLC, said the project continues to affect employees and customers. "It's not earth shattering, it's just super inconvenient," Bell said. "And in combination with the other bridge being out as well, there's really no good alternative." The 27th Street Bridge is also closed for I-94 East-West construction and won't reopen until summer 2027, while projects near the 35th Street Bridge and on West National Avenue have further impacted traffic.

Corey Zetts, executive director of Menomonee Valley Partners, said the partial reopening in August made an immediate difference for the roughly 125 companies and 7,500 employees in the Valley. Her organization hosted a meeting in early October with businesses, the city and WisDOT to discuss major construction projects. "Regular updates from the city and WisDOT are keeping us informed on progress so we can plan effectively, but we are all very much looking forward to all the viaducts reopening and reconnecting our neighborhoods," Zetts said.

Ald. JoCasta Zamarripa, who represents the area, said she spoke with the City Engineer early Tuesday. "I'm disappointed and frustrated on behalf of my constituents. It's unfortunate but just has to be," she said. Zamarripa, recently elected to become the next secretary of state, noted that the south end of the bridge is open and encouraged residents to use that route, which she recently began taking to work herself.