Nevada Gaming Regulators Press Bally's on Tropicana Site Timeline as 2028 Ballpark Deadline Looms

Gaming Control Board Chairman Mike Dreitzer told Bally's executives the stalled redevelopment of the former Tropicana site is 'not acceptable,' warning of 'much, much less patience' next year. Bally's chairman Soo Kim insisted the project 'will land as planned,' but declined to detail construction timelines for the access and parking structures the A's ballpark depends on.

Nevada Gaming Regulators Press Bally's on Tropicana Site Timeline as 2028 Ballpark Deadline Looms

LAS VEGAS — Nevada's top gaming regulator on Thursday publicly challenged Bally's Corp. over the pace of redevelopment at the former Tropicana site, warning that the company's timeline for building access roads and parking around the incoming Athletics ballpark is no longer a matter of wait-and-see.

Gaming Control Board Chairman Mike Dreitzer told Bally's Chairman Soo Kim that the condition of the 27-acre parcel at Tropicana Avenue and Las Vegas Boulevard — one of the most recognizable intersections in the world — has become a source of serious concern.

"One of the most iconic corners, one of the most iconic cities in the world, we seem to be sort of at the bottom of the barrel here," Dreitzer said during the exchange.

The pressure comes as construction on the A's ballpark moves forward on nine acres of the 36-acre site, which is owned by Gaming and Leisure Properties Inc. GLPI carved out the stadium parcel for the Athletics, leaving the remaining 27 acres for a future Bally's resort. Bally's is responsible for the infrastructure that will connect the ballpark to the Strip — parking lots and podium structures that fans will use to reach the stadium.

The question hanging over the project is whether that access will be finished in time for the ballpark's scheduled opening in 2028.

Kim told regulators he remains confident. "We're quite confident that all of these will land as planned," he said. "The project is very important to us as well. It's hard to be a global game company if you don't have a presence and a strong one here in Las Vegas and Nevada."

Dreitzer was unmoved by the assurances. "It's your responsibility to finish all these projects in the best way you can," he said. "It isn't a matter of, 'Hey, let's see what happens,' especially in the state of Nevada. That's not acceptable."

Kim said the company understands the stakes. "We're very supportive of it landing correctly," he said. "We understand our responsibilities and we don't intend to let the state or the board or the county or the city down."

The scrutiny arrives as Bally's pursues an aggressive expansion beyond Nevada, including new projects in New York and Illinois and the acquisition of a Louisiana property — a growth strategy that has raised questions about whether the company's attention and capital are stretched thin.

Clark County commissioners in August approved the first phase of development, signing off on Bally's applications for parking and podium structures for fan access. The Stadium Authority discussed the ballpark site at its November meeting; its next meeting is scheduled for Dec. 3.

Dreitzer said he intends to revisit the timeline during follow-up conversations with the board next year, and he made clear the tone will shift. He promised "much, much less patience about where that stands."

For residents and businesses near the site, the stakes extend beyond a single casino project. The corner has sat largely dormant since the Tropicana was demolished, and the ballpark's success depends on whether fans can actually reach it. A delayed or incomplete access plan could leave the stadium isolated and the surrounding neighborhood without the promised economic activity.

Bally's did not provide specific construction dates for the podium structures when asked.