Nevada Gaming Regulators Press Bally's on A's Stadium Infrastructure Timeline

At a special meeting, Nevada Gaming Control Board Chair Mike Dreitzer told Bally's controlling shareholder Soo Kim that critical infrastructure for the $2.1 billion Athletics stadium must be ready before the 2028 season, expressing doubts about the company's commitment amid its other multibillion-dollar projects.

Nevada Gaming Regulators Press Bally's on A's Stadium Infrastructure Timeline

Nevada gaming regulators on Thursday pressed Bally's Corp. to guarantee that essential infrastructure for the planned $2.1 billion Athletics stadium on the Las Vegas Strip will be completed before the 2028 baseball season, voicing skepticism about the company's focus given its simultaneous construction of major resorts in Chicago and New York.

During a 10-minute hearing at a special Nevada Gaming Control Board meeting, Chairman Mike Dreitzer told Soo Kim, managing partner of Standard General and Bally's controlling shareholder, that parking, utilities and connecting infrastructure must be in place for the stadium's opening. Kim assured the board that those elements would be ready by April 2028, but acknowledged that the broader mixed-use development surrounding the ballpark—featuring shops, restaurants and entertainment—would not be finished until at least 2031.

"Our obligations are part of the deal with the A's, but this is a three-party deal," Kim said, referring to the agreement among Bally's, the Athletics and Gaming and Leisure Properties, the real estate investment trust that owns the land. He added that the company believes "there's still plenty of time for us to build our podium that connects the corners to the stadium as well as a shared accessway that connects the podium, the stadium, the utilities and the parking."

Dreitzer did not mince words about his concerns. "As a fiduciary to the state of Nevada, I have some significant concerns because in what is probably one of the most iconic corners and one of the most iconic cities in the world, we seem to be sort of at the bottom of the barrel here, relative to what's going on," he said. "I have significant concerns about how this situation gets resolved."

The hearing was originally scheduled for an unrelated matter—Bally's acquisition of a European online gaming company that supports Caesars Entertainment's World Series of Poker—but Dreitzer used the occasion to scrutinize the stadium project. He noted that Bally's will likely have to appear before the board again early next year for various approvals, and warned that the board's patience is limited.

"I wanted to make sure that here in November of 2026, you and I are having this conversation because, again, as a fiduciary to the state of Nevada, we're watching this very, very closely," Dreitzer said. "There's an argument that stadiums and teams are for the whole city and they're effectively owned by the whole city. It's such an important item for us that 'We'll see what happens' is not good enough. It has to happen."

Gaming and Leisure Properties has told the Las Vegas Stadium Authority that it would increase its financial investment from the current $125 million to ensure essential infrastructure is completed on time, according to Kim.

The project has faced criticism that Bally's is stretched too thin, attempting to develop multiple multibillion-dollar projects simultaneously while placing the Athletics stadium at the bottom of its priorities. The company is currently building resorts in Chicago and New York, in addition to the Las Vegas development.

Two hours after the special board meeting, the Nevada Gaming Commission approved the board's recommendation on the unrelated licensing matter, but commissioners did not address the stadium project.

The Athletics are scheduled to begin play in their new Las Vegas ballpark in 2028. The surrounding development, which Bally's has described as a multiphased commercial area, remains years away from completion, raising questions about the fan experience and economic benefits promised to the region.

For local residents and taxpayers, the exchange underscores the high stakes of the stadium deal and the pressure on Bally's to deliver on its commitments. With the board vowing to monitor progress closely, the company's next appearances before regulators will be watched as a key test of whether the project stays on track.