A peer-reviewed analysis of 403 major data centers found they consumed nearly 2% of U.S. electricity and emitted 25.7 million metric tons of CO2 annually, with Virginia, Iowa and Ohio accounting for about half. Researchers say industry secrecy forced them to reconstruct facility locations from satellite imagery.
The largest data centers in the United States collectively emit an estimated 25.7 million metric tons of carbon dioxide each year â a carbon footprint roughly comparable to that of entire nations such as Bolivia or Denmark, according to a new peer-reviewed study.
The research, published this month in the journal Nature Sustainability, offers the first peer-reviewed accounting of emissions from the country's biggest data centers since the artificial intelligence boom began. A team led by Harvard University scientists examined the electricity use and carbon emissions of 403 facilities between May 2024 and April 2025.
Together, those data centers consumed nearly 2% of all U.S. electricity â more than New York City and Los Angeles combined â and accounted for about 0.5% of national carbon dioxide emissions, the primary greenhouse gas driving global warming.
Just three states â Virginia, Iowa and Ohio â produced about half of the estimated emissions. Virginia alone accounted for more than a quarter of the total. In PJM Interconnection, the regional grid operator serving Virginia, roughly 60% of the electricity powering data centers comes from fossil fuels. By contrast, states such as Oregon showed lower emissions per unit of electricity because a larger share of their power is generated without fossil fuels.
Across all 403 facilities, 54% of electricity came from burning fossil fuels, primarily natural gas and coal.
Much of the research required investigative work, reflecting the limited public information about AI companies' operations. With no public list of data centers available, the researchers started from a commercial dataset whose licensing rules barred them from publishing facility addresses, names or owners. They then spent hours analyzing building footprints and satellite imagery to confirm locations and sizes, estimated electricity consumption, and calculated emissions based on the fuel mix of the regional power grids serving each site.
"The fact that we had to go through such an extensive reconstruction process just to understand where the infrastructure is and how large it is tells you something about the lack of transparency itself in the industry," said Gianluca Guidi, the Harvard scientist who led the team.
Michael Thomas, who runs the energy data firm Cleanview and was not involved in the study, contrasted data centers with power plants, which must publicly report detailed environmental information. Compiling data center details, he said, requires sifting through millions of documents scattered across county, state and federal databases.
"We've had, like, a half dozen senators reach out to us. They're like: 'How many data centers are there? We're trying to write a bill,'" Thomas said. "Why is the Senate reaching out to me and not EIA or FERC?" he added, referring to the U.S. Energy Information Administration and the Federal Energy Regulatory Commission.
While states including Virginia and Ohio have begun moving toward stricter oversight, Guidi said the federal government should require operators of large data centers to publicly disclose their electricity use and emissions.
"Communities shouldn't need a team of Harvard researchers to analyze satellite images to understand their environmental impact," he said.
Developers have multiple tools to obscure the energy and carbon effects of their projects, and that secrecy has become a central concern in the growing local resistance to data centers nationwide. In this month's midterm elections, voters chose to limit or block data center development in 40 of 41 relevant local ballot measures.
"Non-disclosure agreements, hidden end users and closed-door negotiations frame opposition narratives more consistently than any other concern," according to a recent report by Relae, a climate and energy consultancy.
Between March 2024 and early November, local opposition blocked or delayed at least 70 AI data center projects across 25 states, representing an estimated $271 billion in investment, according to Relae. Fourteen of those projects were in Virginia, the heart of the data center boom.
The study's figures likely underestimate total U.S. data center emissions because the facilities examined do not constitute a complete inventory. The researchers excluded hundreds of possible data centers they could not sufficiently verify, as well as facilities that bypass the grid by drawing power from on-site generators.
The analysis is also a snapshot of a rapidly expanding industry. The average facility in the study had an electrical capacity of about 40 megawatts, while upcoming projects such as Meta's 5-gigawatt Hyperion campus in Louisiana will have more than 100 times that capacity.
Outside researchers said the study provides a crucial baseline for understanding the climate implications of the AI build-out.
"It resets our understanding of these large data centers that are already operating, that they use maybe more power and emit more greenhouse gas emissions than we had thought," said Eric Masanet, who researches emerging environmental technologies at the University of California, Santa Barbara.
Whether the growing emissions represent an acceptable environmental cost should depend on how useful AI proves to be, said Andy Masley, an independent researcher who analyzes data centers' environmental effects.
"I don't really think it makes sense to look at an industry and just say, 'Oh, because it's growing and it's going to make up a meaningful percentage share of American emissions, that must mean it's bad,'" Masley said. "Part of the reason they're emitting so much is just that they're being used by so many people."
As the number of users grows, so will the carbon footprint. While the study represents the most thorough accounting to date of data centers' emissions and electricity consumption, it is already outdated: Since the study period ended May 1, 2025, at least 250 more data centers have come online, according to Cleanview's data.