Jacksonville is considering a $55.4 million incentive package for Gateway Jax's 19-story Riverfront Plaza tower, just weeks after approving nearly $50 million for the developer's Publix project. City officials and residents are asking what protections exist if the hotel and condos underperform.
Jacksonville is weighing a new $55.4 million incentive package for Gateway Jax's proposed 19-story Riverfront Plaza tower, a request that comes just weeks after the City Council approved nearly $50 million in revised incentives for the developer's downtown Publix project. Combined, the two deals would put more than $105 million in potential public support behind Gateway's downtown ambitions.
The Riverfront Plaza proposal calls for a high-rise on a one-acre site overlooking the St. Johns River, featuring a hotel, 50 condominiums, two restaurants and a public terrace. The property was acquired by Gateway through a June 2025 city land swap tied to plans for a University of Florida graduate campus downtown.
Under the proposed terms, the city would provide up to $35.397 million through a REV grant, returning 75% of eligible incremental property-tax revenue generated by the completed project over 20 years, subject to the agreement's terms and cap. A separate $20 million completion grant would be paid only after the project is finished, and would require a subsequent legislative appropriation.
Both incentives would be drawn from the Downtown Northbank Community Redevelopment Area Trust Fund rather than the city's general fund. Gateway says the Downtown Investment Authority has committed to funding the $20 million completion grant, which has been budgeted since the original land-swap legislation. The CRA is funded through property-tax revenue generated within the redevelopment area.
Gateway Jax CEO Bryan Moll said the company has closed on the property, completed independent third-party underwriting and worked with the city and the Downtown Investment Authority on the updated agreement. In a statement, Moll said independent underwriting by the DIA projects a three-to-one return on the incentive package. That projection includes additional property-tax revenue, contributions from condominium owners toward park maintenance and programming for 30 years, and a hotel contribution equal to 2% of additional room revenue to the Downtown Economic Development Fund.
The developer's return estimate depends on assumptions about hotel performance, property values, revenue projections and the time period used. The proposed legislation also authorizes changes to the property's deed. The original agreement included provisions allowing the city to buy the property back if Gateway missed certain construction and financing deadlines.
Questions remain about what happens if construction is delayed, if hotel or condominium sales underperform, and what contractual protections the city retains if Gateway does not meet its construction and financing commitments. City Council President Nick Howland and Finance Committee Chair Will Lahnen did not respond to requests for comment on the proposed agreement, the projected return and the protections for the city.
The debate over the Riverfront Plaza package comes as Jacksonville officials continue to weigh the costs and benefits of using tax incentives to spur downtown development. For residents, the central question is whether the promised returns materialize, and who bears the risk if they do not.