MBTA Plans 100 Service Outage Days in 2027, Down Sharply From 274 in 2024
The MBTA announced a 2027 construction schedule with 100 days of planned service outages, a steep decline from 274 days in 2024, as track and signal upgrades take hold. Most subway disruptions will occur on weekends, with major work on the Red and Orange lines and the Green Line's central tunnel.
The MBTA unveiled its 2027 construction schedule on Thursday, projecting 100 days of planned service outages â a sharp drop from the 274 diversion days riders endured in 2024, the agency said.
The number of disruption days has fallen steadily: from 274 in 2024 to 190 in 2025 and 132 this year, according to the T. The 2027 plan continues that trend as major investments in track, signals and other infrastructure deliver faster, more reliable trips, officials said.
"In 2023, 65% of the system was found to be out of State of Good Repair," Interim Transportation Secretary and MBTA General Manager Phillip Eng said in a statement. "The work we've performed since 2024 during weekend and multi-day outages is showing incredible, tangible progress for our riders â we've replaced hundreds of thousands of feet of rail, upgraded much of our signal infrastructure, and enhanced so many other areas of the system."
Eng added: "The new way the MBTA does business works! And our riders are feeling our commitment to that progress every day." He thanked the public for its patience.
Most subway service interruptions in 2027 will take place on weekends to minimize disruptions, the agency said. The work will focus on completing major signal upgrades on the Red and Orange lines and finishing signal improvements in the Green Line's central tunnel ahead of the arrival of new Type 10 vehicles. Track maintenance will continue across all lines.
In an unusual move, the T published every anticipated shutdown for the year. The dates are subject to change.
On the Green Line, Symphony Station will remain closed through spring 2029 for accessibility improvements, including four new elevators at the 85-year-old station. Central tunnel signal work will suspend service between North Station and Babcock Street (B branch), Kenmore (C and D branches) and Heath Street (E branch) on several dates in January and February, with weekend tunnel inspections in September. The Hammond Street Bridge in Newton will force suspensions between Reservoir and Riverside in August. Track revitalization will halt service between Government Center and East Somerville and Union Square for nine days in November, with an extension to Medford/Tufts on the first weekend to remove the Broadway Utility Bridge. Accessibility upgrades on the B branch will bring weekend suspensions between Babcock Street and Boston College in December.
On the Red Line, tunnel inspections will close the line between Alewife and Kendall/MIT for a weekend in January. Signal pre-commissioning work will suspend service between JFK/UMass and Quincy Center for five days in April, and between Broadway and North Quincy on the Braintree branch and Broadway and JFK/UMass on the Ashmont branch for a weekend in April. Single-track operations between Quincy Adams and Braintree are scheduled for several days in March and April. Systemwide radio upgrades and tunnel inspections will close the line between Kendall/MIT and JFK/UMass for two weekends in July. Track revitalization and Furnace Brook Parkway Bridge work will suspend service between JFK/UMass and Braintree for nine days in August, and single-track operations between Alewife and Harvard are planned for two weekends in November for radio upgrades.
On the Orange Line, tunnel inspections and Ruggles Station improvements will close service between Back Bay and Forest Hills for a weekend in March. Track revitalization will suspend service between North Station and Ruggles for nine days in May. Radio upgrades will close the line between North Station and Back Bay for a weekend in July, and construction of two new accessible transfer elevators at Downtown Crossing will halt service there for four days in October.
The Mattapan Line will see weekend track work between Ashmont and Mattapan in March and April. On the Blue Line, track revitalization will suspend service between Bowdoin and Airport for 10 days in June, and radio upgrades will close the line for a weekend in October.
Commuter Rail riders will face off-peak weekday disruptions on the Needham and Newburyport/Rockport lines for tie work from March through June. The South Station Tower One project will suspend all lines between South Station and Braintree and between Back Bay and Forest Hills on two weekends in March and April. Foxboro and Walpole service will be suspended on several dates in March and April. The Worcester Line will see weekend suspensions between Back Bay and Framingham in June for track upgrades at Newtonville. Work at South Station's Cove Interlocking will affect schedules on the Needham, Worcester, Providence/Stoughton and Franklin/Foxboro lines on several three-day stretches from June through October. The Lowell Line will be affected by removal of the Broadway Utility Bridge in November.
Separately, the MBTA said weekday ridership topped one million in October for the first time since the pandemic.