Local
Split Bridge Joint on I-285 Over Chattahoochee Triggers Hours-Long Weekend Gridlock
A failed header joint on the I-285 bridge over the Chattahoochee River forced emergency repairs Saturday night, stranding drivers for over an hour and reigniting frustration over chronic weekend roadwork on the west side.
ATLANTA â A failed joint on the I-285 bridge over the Chattahoochee River brought traffic to a standstill Saturday night, trapping motorists for more than an hour as state crews rushed to make emergency repairs, the Georgia Department of Transportation said.
The problem was a bridge header joint that split open, GDOT said. The agency stressed there was no structural danger to the bridge and that crews patched the joint. All lanes have since reopened.
For drivers like Keith Harris, the closure turned a short trip into an ordeal. Harris said his GPS initially estimated a six-minute delay as he approached the bridge.
"And then all of a sudden, traffic just stopped moving totally, and we maybe moved 50 feet in about an hour and 10 minutes," Harris said.
Harris described a scene of confusion as motorists tried to figure out what had happened. Some got out of their vehicles; others climbed onto car roofs to see how far the backup stretched.
"You saw people doing a little bit [of] everything, trying to figure out what was going on, trying to stand on the roof of cars to see how far they could see," he said.
Some drivers eventually gave up, turned around and exited using the South Cobb Drive entrance ramp, according to accounts from motorists.
Harris was headed to his nephew's middle school championship football game when he got stuck. "So I wasn't able to make that, so that was a bummer," he said.
The emergency closure came as GDOT had scheduled work in several areas of I-285 beginning Friday, with work zones set to reopen Monday morning. Permanent repairs to the bridge are planned after next week, the department said.
For Harris and other west-side commuters, the weekend disruption is a familiar frustration. "It's been crazy, especially on this side, on the west side here where we are," he said. "It always shuts down between Pacers Ferry and South Cobb."
He added: "I'll be glad when everything is repaired."
The episode highlights the strain that recurring weekend construction and sudden infrastructure failures place on metro Atlanta drivers, many of whom plan their weekends around highway closures. While GDOT confirmed the bridge is safe, the hours-long backup underscored how quickly a single failed component can ripple across the region's busiest corridors.