A citizen-led petition with more than 11,000 verified signatures has forced a special election that will let Coweta County voters repeal a controversial rezoning for a massive data center campus and ban such facilities countywide.

Coweta County Voters to Decide $17 Billion Data Center's Fate in Jan. 12 Special Election

NEWNAN, Ga. — Coweta County voters will head to the polls on Tuesday, Jan. 12, 2027, for a special election that could halt a $17 billion data center project and ban data centers across the county, following a successful citizen petition drive that gathered more than 11,000 verified signatures.

Probate Judge Carrie B. Markham ordered the election Monday after finding the petition valid. The petition, filed Oct. 16 under the Home Rule provision of the Georgia Constitution, sought a public vote to repeal the county commission's April 7, 2026, approval of a rezoning for the project and to amend the county code to prohibit data centers, data center campuses, cryptocurrency data centers and cryptocurrency mining operations in all zoning districts.

According to Markham's order dated Nov. 23, the petition required 10,971 signatures — 10% of the county's 109,703 active electors in the last general election. The county's director of elections certified Nov. 20 that 11,065 signatures were verified, and Markham found the petition valid.

The ballot question will ask voters: "Shall the action of the Coweta County Board of Commissioners on April 7, 2026 approving REZONE 24-019 be repealed, and Appendix A. Zoning and Development of the Coweta County Code of Ordinances be amended to delete data centers and data center campuses as permitted and conditional uses in all zoning districts and to prohibit data centers, data center campuses, cryptocurrency data centers, and cryptocurrency mining operations in all zoning districts of Coweta County?"

The election will be administered by the Coweta County Board of Elections and director of elections under state law, with the county footing the bill and the court certifying the results.

Along Wagers Mill Road in Newnan, yard signs urging residents to keep data centers out of the county line home after home. Residents interviewed said they welcomed the chance to vote.

"I think it's a good idea, an excellent idea," said Leroy Kenner, a Coweta County resident. "The voters should have the right to decide whether or not the data centers come to Coweta County or anywhere, period."

Jennifer Tedder said she signed the petition. "I just think it's not a good thing for us to have in our community here," she said.

The project, known as Project Sail, is proposed by Atlas Development, LLC, according to Development of Regional Impact filings with the Georgia Department of Community Affairs. The filings describe 13 buildings of about 378,000 square feet each, plus substations, at the intersection of Welcome To Sargent Rd & Wagers Mill, with an estimated completion date of Dec. 31, 2036. The build-out value is estimated at $17,161,900,000, with projected local tax revenue of $163 million per year.

The filings also estimate water demand at 9.1 million gallons per day, sewage flow at 3.03 million gallons per day and solid waste at 800 tons per year, with the Coweta County Water & Sewer Authority listed as the water and wastewater provider.

Atlas Development, based in Buford, filed an objection to the petition that the court received Oct. 23. Markham dismissed the objection in a separate Nov. 23 order, noting that the Georgia Supreme Court has made clear no party has legal standing to object to a petition filed under that provision of the state Constitution, and that the objection was not verified. Atlas representatives did not respond to requests for comment.

Citizens for Rural Coweta, the group behind the petition, celebrated the judge's order.

"We are thrilled with the Judge's order," volunteer Vivian Allen said in a press release. "Thousands of our neighbors signed because they wanted a say, and we can't wait to see Coweta County turn out on January 12."

Fellow volunteer Donna Boles said the effort was grassroots. "This happened because people stood in parking lots, on sidewalks, and at local events collecting signatures in the summer heat," she said. "This vote belongs to them."

Coweta County communications manager Cathy Wickey said in a statement that the county learned of the ruling at the same time as residents and is still assessing its implications. "Given the unique nature of this situation, we are still assessing its potential implications," the statement said. "We anticipate that legal questions and challenges may arise among the entities involved."

The statement said the Elections Department will conduct the special election in accordance with state election laws, using normal election equipment and precincts.

The vote comes as communities across Georgia and the nation grapple with the land, water and energy demands of large-scale data centers, and as local governments face growing pressure to give residents a direct say in decisions with long-term environmental and fiscal consequences.