Coweta County Residents Force January Vote on $17 Billion Data Center
A probate judge has cleared the way for a special election on Jan. 12, 2027, where Coweta County voters will decide whether to kill a proposed $17 billion data center. Organizers gathered more than 11,000 signatures in just over a month to force the first-of-its-kind vote.
COWETA COUNTY, Ga. â Residents here will get the final say on a proposed $17 billion data center after a probate judge this week validated a citizen petition and ordered a special election for Jan. 12, 2027.
Probate Judge Carrie B. Markham ruled Monday that the petition, filed under Georgia's home rule statute, met the legal requirements to force a referendum on the project known as Project Sail. The decision also dismissed a legal objection filed by the developer, Atlas Development, LLC.
The fight over Project Sail has been brewing for more than two years, with multiple town halls and community meetings drawing heated opposition from residents concerned about the facility's size, its environmental impact and its demand on local infrastructure. The project, proposed by Atlas Development, would be one of the largest data center campuses in the state.
The petition effort began Oct. 16 and quickly surpassed expectations. The Coweta County Director of Elections verified 11,065 signatures â about 100 more than the 10,971 required to place the measure on the ballot. Organizers with the group Citizens for Rural Coweta said volunteers collected signatures in parking lots, on sidewalks and at local events through the summer heat.
"The Coweta County Probate Court found our Home Rule petition valid and called a special election. We are very pleased with the Judge's order," the group said in a statement. "Thousands of you signed, and volunteers stood in parking lots, on sidewalks, and at local events collecting signatures in the summer heat to make it happen."
If voters approve the measure, it would amend the Coweta County Code of Ordinances to remove sections that allow permitting and conditional-use zoning for data centers, data center campuses and cryptocurrency mining operations â effectively blocking such development in the county.
Atlas Development had filed a legal objection to the petition, but the court dismissed it, citing Georgia Supreme Court precedent that no party â including a company or county government â has legal standing to challenge a properly filed petition. Under state law, once signatures are verified, the question must go to voters.
The developer did not immediately respond to a request for comment. Earlier in the process, the company said it remained committed to Project Sail and to engaging with the community.
The special election is scheduled for Jan. 12, 2027. It is believed to be the first time Georgia voters will decide the fate of a data center project at the ballot box, a development that could set a precedent for other communities grappling with the rapid expansion of the industry.
For Coweta County residents, the vote represents a rare direct exercise of local democracy over a project with enormous economic and environmental stakes. Supporters of the data center have pointed to potential tax revenue and jobs, while opponents have raised concerns about energy consumption, water use and the loss of rural character.
With the court's ruling, the decision now rests solely with the voters.